This 18,720 sf two-story facility was designed adjacent and
connected to an existing single-story telecommunications
equipment building that had been designed by KDW in the
previous year.
One of the most critical elements of this project was the
complete replacement of all major HVAC and power systems for
both new and existing spaces. The resulting facility
includes switchgear, colocation, 600 kW generator, ASSD fire
detection system, and a 200 ton N+1 HVAC system.
The exterior design features a split block CMU face that
ties in to the existing structure, with colorful metal
siding details. A new colored metal roof mansard with a
parapet helps screen the rooftop equipment. Site work
included new utilities, landscaping, curbs and walks, and a
new security-fenced parking area.
By using careful project phasing and temporary utility
support systems, the telecommunications equipment in the
existing facility remained 100% operational throughout
construction.
|



|