KDW was hired to build a new Data Center on the ninth
floor of an existing 12-story building in downtown Seattle.
The scope of work entails the removal of carpet, dropped
ceiling, and existing ductwork, lighting and fire alarm
systems, the installation of seismic restraint systems as
well as a new 24” raised access flooring system to
accommodate cooling and computer cabling, and upgrades to
all mechanical and electrical systems including back-up
power. The resulting space will provide a new 6,000 sf
computer room, a 600 sf office area, as well as storage and
administrative support space. |

|